Two Spraberry Field Wells Completed by XTO Energy

Drilling Activity Details

Locations

Martin
TX
United States

Operators
Post Date
Shore Type
Well Name
#3072JH Cassidy Unit 1, #3073JH Cassidy Unit 1
Geo Coordinate

Drilling Activity Summary

Description

XTO Energy Inc. completed two Spraberry Field wells in T&P RR Co A-776 in Martin County (RRC Dist. 8), Texas. The #3072JH Cassidy Unit 1 has a total depth of 19,437 ft and a true vertical depth of 7,815 ft. The well was kicked off at 8,068ft. It pumped 812 bbl of 40.7° API oil, with 700,000 cu ft of gas per day. Production is from perforations at 8,981-19,303 ft after fracturing. The #3073JH Cassidy Unit 1 was drilled to 19,310 with a true vertical depth is 7,817 ft. It was tested pumping 756 bbl of 40.7° API oil and 700,000 cu ft of gas per day. Production is from perforations between 8,850 ft and 19,175 ft. XTO is a subsidiary of Exxon Mobil.